Understand your point - but you can split nuclear into smaller phases too and phase them in.

Solar and wind aren't immune to this either. You don't want to generally build things say 10MW at a time - that would require 100 rounds of planning, regulator approval, engineering design and the like for a big utlity scale solar and wind plant. You generally do it in big chunks too. And there have been big holdups especially in getting grid interconnect.